Northeast
Engineers & Consultants, Inc was contracted
to perform a geotechnical investigation and preliminary
structural design for Additions to the Squadron
Operation Building at the Quonset Air National
Guard Base in North Kingston, Rhode Island. The
development consisted of additions and renovations
to the existing Squadron Operations Facility.
These additions encompassed approximately 6,300
square feet, and included first floor extensions
to the north and south sides of the eastern portion
of the building and a second story to the existing
building at the same end. The existing building
interior will be modified and new pitched standing
seam metal roof will be constructed over the entire
structure.
The existing building is a one story structure
with a structural steel frame and masonry walls.
It has a flat steel truss roof and a six-inch
thick reinforced concrete slab floor. The building
is supported on a pile foundation consisting of
20-ton capacity treated timber piles that are
25 feet long with a minimum butt diameter of 12
inches.
NE&C's scope of work included the following
tasks:
- Field exploration that included drilling four
borings to a 40 foot depth
- Laboratory testing
- Engineering analysis
NE&C's borings encountered three distinct
zones of subsurface materials; fill, soft organic
soil, and medium dense to dense sands. This fill
layer extends to a depth of the 10 to 11 feet
from existing grade, and is underlain by a layer
of soft peat. The peat layer is about 3 to 5 feet
thick. Fine to medium sand was encountered beneath
the peat to the full depth of the borings.
The layer of peat and portions of the existing
fill are soft and loose and susceptible to compression
and consolidation upon the application of structural
loads that could have resulted in significant
settlement of the ground surface and any overlying
structures. Piles were needed for the foundation
of the first floor lateral additions; some of
the existing interior pile caps also needed to
be supplemented with new piles where new loads
from the second story exceeded the capacity of
the existing piles.
Other methods of reducing potential fill settlement
included overexcavation of all loose and soft
soils and replacement with compacted engineered
fill, or ground modification to strengthen and
reduce the compressibility of the soft and loose
soils. These options would have allowed the use
of shallow footings rather than piles. Overexcavation
was not recommended because the depth of removal
would have been well below the groundwater table
and thus would have required extensive dewatering
and stabilization of the bottom. Also, the overexcavation
would have had to be performed immediately adjacent
to the existing building, requiring shoring and
possible underpinning to prevent distress to the
structure. The weight of the additions supported
on spread footings could have also surcharged
the existing piles beyond their design capacity.
This option would have also been significantly
more expensive than piles.
Ground modification that may have been appropriate
for the site conditions include jet grouting,
vibro-replacement, or soil mixing. Each of these
methods would have involved the injection of grout
or stone into the subsurface to strengthen the
soft and loose soils. Since these methods would
have involved specialized equipment and experienced
specialty contractors, they would have been significantly
more expensive than piles considering the relatively
small size of the project.
|