Introduction
This report presents a summary of the geotechnical
issues regarding the design and construction of
the two schools on Springfield Street and Hartford
Avenue in the City of Providence. This report
is based on my recollections and a recent review
of the project files at Northeast Engineers &
Consultants, Inc.(NE&C). I provided geotechnical
consultation during design and construction of
the project while serving as an outside consultant
to NE&C prior to my joining the firm full-time
in August 1999.
NE&C was part of the design build team for
the project led by O. Ahlborg & Sons, Inc,
and provided the geotechnical and civil engineering
consultation and design. The project was designed
and constructed in the spring and summer of 1999.
It consisted of the construction of an elementary
school and a middle school on the site, plus paved
parking areas and landscaping.
Subsurface Conditions
The site was known to be a previous dumping area.
Test borings were drilled in March and April 1999
to explore the subsurface conditions in order
to determine the most appropriate foundation design
for the two schools. The borings indicated that
the middle school site was underlain by a layer
of fill that was roughly between 10 and 20 feet
thick. The fill was found to consist of soil,
debris, rubble, brick, glass, ash, cinders, and
wood. In most areas, there was a 5 to 10 foot
thick layer of organic silt and peat beneath the
fill. Beneath the peat was dense to very dense
native sandy soil. The depth to the top of the
dense sand layer ranged from about 10 to 25 feet
within the building footprint.
Test pits excavated in the elementary school
footprint encountered fill to a depth of 12 feet
or less, underlain by dense native sands. No organic
silt or peat was found beneath the elementary
school.
Groundwater was encountered at depths of between
8 to 12 feet below the ground surface.
Foundation Design
Various options for support of the two schools
were evaluated. The existing fill and the organic
soil and peat were considered compressible and
likely to cause settlement of any buildings placed
on them. Removal of the fill and replacement with
compacted engineered fill was determined to be
cost effective for the elementary school due to
the shallow depth of the fill, but not for the
middle school since the fill was much deeper and
extended well below the groundwater table. Removal
and replacement of the fill with engineered compacted
fill would allow the elementary school to be constructed
with conventional shallow footings and a slab-on-grade
floor.
It was determined that a pile foundation would
be the most appropriate and cost effective design
for the middle school foundation. Piles transfer
the structural loads of the building through the
compressible fill and organic soil to the dense
native soils, thus preventing settlement of the
structure. The floor of the middle school was
selected to be a structural slab, being totally
supported by the pile foundation and not deriving
any support from the ground surface. This is in
case the ground surface undergoes any settlement
after construction.
Different pile types were considered. Steel pipe
piles filled with concrete were selected over
timber piles due to their higher load bearing
capacity and their ability to be installed at
the correct lengths by cutting off or splicing.
The piles were designed to achieve capacity by
friction in the dense native sands. The selected
design was a 12 inch diameter closed end steel
pipe pile filled with concrete with an allowable
vertical downward capacity of 40 tons. To achieve
the design capacity, a minimum required embedment
into the native dense sand below the fill was
determined. The total pile depth would be the
depth to the top of the bearing layer plus the
embedment depth.
The middle school foundation was designed as
a system of pile caps interconnected with grade
beams and topped by a structural slab. Each pile
cap supported concentrated column loads and included
between 2 and 6 piles. The grade beams around
the perimeter of the building extended below the
final exterior grade for frost resistance.
Construction
A representative from NE&C monitored the
pile installation on a full-time basis. Blow counts
were recorded to allow us to verify that the piles
were driven into the bearing layer to the minimum
embedment depth. A total of about 750 piles were
driven in April, May, and June 1999. Total pile
depths ranged from about 31 to 70 feet.
Load tests were performed on three of the piles
to confirm the pile design. The piles were loaded
to twice the design capacity and no signs of failure
were detected. Based on our observations and load
test results, we concluded that the piles were
driven to the design capacity and would provide
a suitable foundation for the building.
Settlement
The middle school was designed with a pile foundation
and structural slab due to the potential for settlement
from the imposed load of the building. The elementary
school was constructed on engineered fill. The
amount of settlement of the building foundations
that may possibly occur from the structural loads
would not be considered significant from a structural
viewpoint. No distress or significant cracking
to the buildings and floors would be expected.
Fills can also compress over time due to their
own weight or due to decomposition of organic
materials. This could lead to settlement of the
ground surface beneath the middle school or the
surrounding area. However, due to the age and
nature of the fill, we would expect this type
of settlement to be relatively small after the
building construction. The organic soil beneath
the fill and the fill itself would have been compressed
by the surcharge weight of the overlying fill
over the 30 or more years since it was placed,
so the amount of additional consolidation in the
future would be expected to be minor. The possibility
of settlement of the ground surface exposing the
underside of the middle school building is considered
remote, since the exterior grade beams extend
below grade. In any case, there would be plenty
of time to correct any significant settlement
around the building if it occurred well before
it exposed the bottom of the foundation to the
outside. At the present time, over 3 years after
construction, we are not aware of any reported
settlement of the building or the surrounding
ground surface.
Limitations
This report is based on my recollections and
a review of currently existing project files.
This information is solely about the geotechnical
issues of the project. Our geotechnical consultation
was performed in general accordance with standards
of local geotechnical engineering practice at
the time that they were performed.
|